Differences between SD and PG - Works Contracts



DIFFERENCES BETWEEN  ( In Works contracts)

Features

Security Deposit (SD)

Performance Guarantee (PG)

Object

In token for the due fulfilment of the contract

In token for the purpose of successful performance by the Contractor to execute the work. Introduced in lieu of risk action procedure (contracts rescinded due to failure of contractors) 

Due Date

EMD/Bid Security of successful tenderer will be retained as part S.D., balance will be recovered at the rate of 6 % of the bill amount till the full Security Deposit is  recovered,


Obtained from successful bidder after issuance of LOA, but within 60 days of issue of LOA.

a)      Within 21 days from LOA – No interest

b)      22 to 60 days from LOA – penal Interest 12 % per annum

Balance

Balance Security Deposit will be recovered only from the running bills of the  contract and no other mode of collecting SD shall be permitted

Submit the Performance Guarantee in any of the forms i.e., Cash, Irrevocable Bank Guarantee, Govt securities, DDs of nationalized banks, Post office SB deposit, NSCs etc.

If fails

There is no question of failing to submit the balance SD, because the same is recovered from running bills at the rate of 6 % of bill amount till the full SD is recovered.

In case the contractor fails to submit the requisite PG even after 60 days from the date of issue  of LOA, the contract shall be terminated duly forfeiting EMD and other dues, if any payable against that contract. The failed contractor shall be debarred from participating in re-tender for that work.

Releases

Can be released subject to

A. Physical completion of the work and Maintenance period if any.

B. After passing Final Bill

C. Obtaining the No Claim certificate from the Contractor

D. Obtaining the No Dues certificate against   Contractor from the Executive

Can be released immediately after physical completion of the work.

                                                                 


Thursday, December 5, 2024

EMD & SD in Stores - Differences between

                                        


                                    
  Differences between EMD & SD in Stores 

EMD 

Earnest Money Deposit

SD

Security Deposit

Calculated on 

Tender Value

Contract value 

Rounded off to nearest higher

Rs. 10

Rs. 10

Up to Rs. 25 Lakhs

Nil

Nil

 

Rs. 25 Lakhs to Rs. 50 Crore

2%

5%

Maximum is Rs.20 Lakhs

Maximum is Rs. 50 Lahs

Above Rs. 50 Crore

Fixed Rs. 50 Lakhs

Fixed Rs. 1 Crore

(Global Tenders - No ceiling)

Valid for 

Final bid validity period plus 45 days 

Date of completion of all contractual obligations plus 60 days

If not submitted

Offers shall be summarily rejected

The EMD shall be forfeited and case be dealt with as that of withdrawal of offer by the Tenderer as per extant instructions

EMD 

Earnest Money Deposit

SD

Security Deposit

Forfeit 

If withdraws the Offer within validity  or 

If not submit the balance SD within 21 days in case of awarding the Stores contract

In case of failure by the Supplier to meet deliveries for any lot, Railway may cancel the Contract for default part by forfeiting SD commensurate to that lot

Exempted cases

1.Up to Rs. 25 Lakhs 

2. Govt Depts

3. Other Railways

4. Indian Ordnance factories

5. Railway PSUs

6. MSEs

1.Up to Rs. 25 Lakhs 

2. Govt Depts

3. Other Railways

4. Indian Ordnance factories

5. Railway PSUs

Exempted for Single Tender / PAC items

Hqrs: 

1. Personal Approval of TAA, not below the level of PCMM.

2. Finance concurrence not required

3. Decided on case to case basis 

4. Suitably incorporated in the Tender conditions

Field Units: 

1. Personal approval of TAA, but not below the SAG level 

2. Finance concurrence is required

3. Decided on case to case basis

4. Suitably incorporated in the Tender conditions

Hqrs: 

1. Personal Approval of TAA, not below the level of PCMM.

2. Finance concurrence not required

3. Decided on case to case basis 

4. Suitably incorporated in the Tender conditions

Field Units: 

1. Personal approval of TAA, but not below the SAG level 

2. Finance concurrence is required

3. Decided on case to case basis

4. Suitably incorporated in the Tender conditions

Debarment - exemption in case of False declaration 

6 Months

6 Months



Note: 

  1. In exceptional cases, Railways reserves the right to increase the upper ceiling of Security Deposit, up to 10% of the contract value.
  2. SD clause is applicable - Risk purchase clause shall not be applicable 
  3. SD clause is not applicable - Risk purchase clause shall be applicable 

 

LD – Liquidated damages for delayed supply

 

  • 0.5 % of the price of stores per week or part of the week of delay

 

  • Upper limit – 10% of the value of contract (irrespective of delays)

 

end






 

 

Sunday, November 17, 2024

Guarantee Vs Warranty - Differences between


 

Differences between Guarantee & Warranty

 

Area

Guarantee

Warranty

In Simple

General promise of satisfaction

Specific remedies under defined conditions

Definition

A Promise about the quality or performance of a Product

A Written assurance fo repair or replacement of a Product

Scope

Broader

Limited

Cover

Repair, Replacement or Refund

Repair & Replacement only

Legality

Informal & Not legal

Formal, Written & legally binding

Duration

Shorter period

Longer period

Cost

Free of cost

Additional purchase or fees

 

Sunday, November 3, 2024

Approval Vs Sanction अनुमोदन बनाम मंजूरी

 


Differences between Approval & Sanction

Approval and Sanction are two distinct terms often used interchangeably in Indian Railways parlance, but they carry specific meanings. 


Approval

Sanction

First step

Second step

Formal acceptance of a proposal, plan, or project 

Formal authorization to incur expenditure on the said proposal, plan, or project 

Like giving a project the green light

Like giving a project the money to go ahead

Doesn’t involve financial commitment

Involve financial commitment

Abstract Estimate: for Administrative approval

Detailed Estimate: for Technical sanction

Example: Approving New Line and included in the Pink Book (Works Programme)

Example: Sanction of expenditure for construction of New Line by the authorities as per MSOP - Model Schedule Of Powers





अनुमोदन और मंजूरी के बीच अंतर


अनुमोदन और मंजूरी दो अलग-अलग शब्द हैं, जिन्हें भारतीय रेलवे की भाषा में अक्सर एक दूसरे के स्थान पर प्रयोग किया जाता है, लेकिन उनके अर्थ विशिष्ट होते हैं।


अनुमोदन

मंजूरी

पहला कदम 

दूसरा कदम

किसी प्रस्ताव, योजना या परियोजना की औपचारिक स्वीकृति

उक्त प्रस्ताव, योजना या परियोजना पर व्यय करने के लिए औपचारिक प्राधिकरण

जैसे किसी प्रोजेक्ट को हरी झंडी देना

जैसे किसी परियोजना को आगे बढ़ाने के लिए धन देना

इसमें वित्तीय प्रतिबद्धता शामिल नहीं है

वित्तीय प्रतिबद्धता शामिल करें

प्राथमिक अनुमान: प्रशासनिक अनुमोदन हेतु

विस्तृत अनुमान: तकनीकी स्वीकृति के लिए

उदाहरण: नई लाइन को मंजूरी देना और पिंक बुक (कार्य कार्यक्रम) में शामिल करना

उदाहरण: एमएसओपी के अनुसार प्राधिकारियों द्वारा नई लाइन के निर्माण के लिए व्यय की स्वीकृति - शक्तियों की आदर्श अनुसूची