Out of Turn Works - OOT Works
(many
times asked. Very important question for GRP & General expenditure optional)
ü Definition:  Works that are to be undertaken during a year,
provided neither provided in the Sanctioned works in the current year, nor
included in the Sanctioned works of Previous years. 
ü  Execution authority - should justify the need
to undertake the work immediately (though not included in the Sanctioned works)
and also why it could not be anticipated/included in the Pink Book/LAW.
ü Funds should be provided for OOT works - duly re appropriated within
the same Plan Head from the Itemized works.
ü CPDE
- Chief Planning and Design Engineer  
/   CE/P&D - Chief
Engineer/Planning & Design  - Nodal
officer for OOT works in a Zonal Railway. 
ü Prior
Finance Concurrence of PFA/Sr.DFM is required for OOT works in Zonal Railway
& Division respectively.  
ü  Passenger Amenities works :-
1.   Emphasis
/ Importance should be on creation of amenities of durable and lasting nature. 
2.    Funds should not be frittered / wasted on
provision of superficial items like furnishings & furniture etc. 
ü Funds
provided for OOT woks should be duly re appropriated within the same Plan Head
from itemized works. 
ü Safety works under OOT - Should be completed within a maximum period
of 8 months from the date of sanction of Detailed Estimate.  Otherwise, the object of OOT for safety works
itself is defeated. 
ü Before
obtaining Out of turn sanction of GM for traffic facilities/ line capacity
work, approval of PCOM should be taken.  
ü Administrative
approval of GM/DRM as stated below - should be obtained before incurring
expenditure on out of turn basis.
| 
   
Plan Heads 
 | 
  
   
Sanctioning Powers (as per MSOP) 
 | 
  
   
Remarks 
 | 
 |
| 
   
GM 
 | 
  
   
DRM 
 | 
 ||
| 
   
PH 5300- Passengers &
  Other user amenities 
 | 
  
   
2.5 Crores per case 
 | 
  
   
2.5 Crores per case 
 | 
  
   
Annual ceiling of Rs.25 Crores (other than
  Lumpsum grant) for non-safety items.  
This restriction is not
  applicable in case of Safety works. 
 | 
 
| 
   
PH 5200 - Staff amenities 
 | 
  
   
1 Crore 
 | 
  
   
Nil 
 | 
 |
| 
   
Other Plan Heads 
 | 
  
   
2.5 Crores per case 
 | 
  
   
Nil 
 | 
 |
| 
   
M & P Items 
 | 
  
   
10 lakhs per case 
 | 
  
   
Nil 
 | 
  
   
Annual
  ceiling is Rs. 50 lakhs.  However, all
  such proposals together with M&P items sanctioned at CME level under LAW should
  be within the Lump sum grant given by the Board. 
 | 
 
ü
 The above table useful for SOP related questions in the
examination. 
                                                          *****