IRPSM
Ø Full form
is “Indian Railways Projects Sanctions & Management.
Ø That means
it has two broad divisions.  1) Sanctioning of new projects i.e., Works Programme
and2) Management/Monitoring of such sanctioned
Projects.Web based application i.e., usable only with an internet
connection and uses HTTP (Hyper-Text Transfer Protocol) as its primary
communication protocol.
Ø Developed
by CRIS, New Delhi ( All the system administration functions, viz Operating
System, Database, Application Server besides day to day operation –
responsibility of CRIS)
OBJECTS
OF IRPSM 
Ø Online
creation and forwarding of “NEW WORKS” proposals from the Zonal Railways and
Production Units to the Railway Board duly replacing the existing manual
system.
Ø Modifications
to the “Works in Progress”
Ø Printing of
Works programme, Pink Book and other sanction books after sanction by Railway
Board.
Ø Monthly updatingof
status of various works by Executing agencies like Sr.DEN, Sr.DOM etc.
Ø Monitoring
of all Works/Projects.
TYPES OF USERS
| 
   
LEVEL/USER 
 | 
  
   
PLAN HEAD CO ORDINATOR 
 | 
  
   
WORKS PROGRAMME CO ORDINATOR 
 | 
  
   
SANCTIONING AUTHORITY 
 | 
 
| 
   
DIVISION 
 | 
  
   
Branch officers like Sr.DOM, Sr.DME etc 
 | 
  
   
Sr.DEN/Co 
 | 
  
   
DRM 
 | 
 
| 
   
ZONAL RAILWAY 
 | 
  
   
PHODs 
 | 
  
   
CPDE – Chief Planning & Design Engineer 
 | 
  
   
GM 
 | 
 
| 
   
RAILWAY BOARD 
 | 
  
   
- 
 | 
  
   
EDCE(G) – Executive Director Civil Engineering
  (General) 
 | 
  
   
Railway Board & Minister for Railways 
 | 
 
List
of Plan Heads and Plan Head Co-ordinators
| 
   
PH No 
 | 
  
   
PH Name 
 | 
  
   
Plan Head Coordinator 
 | 
 |
| 
   
Divisional 
 | 
  
   
Zonal Rly/PU 
 | 
 ||
| 
   
11 
 | 
  
   
New Lines 
 | 
  
   
Sr.DOM 
 | 
  
   
COM 
 | 
 
| 
   
14 
 | 
  
   
Gauge Conversion 
 | 
 ||
| 
   
15 
 | 
  
   
Doubling 
 | 
 ||
| 
   
16 
 | 
  
   
Traffic Facilities 
 | 
 ||
| 
   
35 
 | 
  
   
Electrification Projects 
 | 
 ||
| 
   
81 
 | 
  
   
Metropolitan transport projects 
 | 
 ||
| 
   
PH No 
 | 
  
   
PH Name 
 | 
  
   
Plan Head Coordinator 
 | 
 |
| 
   
Divisional 
 | 
  
   
Zonal Rly/PU 
 | 
 ||
| 
   
29 
 | 
  
   
Level Crossing Gates 
 | 
  
   
Sr.DEN/Co 
 | 
  
   
CTE 
 | 
 
| 
   
30 
 | 
  
   
ROB/RUB 
 | 
  
   
CBE 
 | 
 |
| 
   
31 
 | 
  
   
Track Renewals 
 | 
  
   
CTE 
 | 
 |
| 
   
32 
 | 
  
   
Bridge Works 
 | 
  
   
CBE 
 | 
 |
| 
   
51 
 | 
  
   
Staff Quarters 
 | 
  
   
PCE 
 | 
 |
| 
   
52 
 | 
  
   
Staff Amenities 
 | 
  
   
PCE 
 | 
 |
| 
   
64 
 | 
  
   
Other Specified works 
 | 
  
   
PCE 
 | 
 |
| 
   
PH No 
 | 
  
   
PH Name 
 | 
  
   
Divisional 
 | 
  
   
Zonal Rly/PU 
 | 
 
| 
   
17 
 | 
  
   
Computerisation 
 | 
  
   
Sr.EDP 
 | 
  
   
CCM 
 | 
 
| 
   
33 
 | 
  
   
S & T 
 | 
  
   
Sr.DSTE 
 | 
  
   
CSTE 
 | 
 
| 
   
36 
 | 
  
   
Other Electrical Works 
 | 
  
   
Sr.DEE 
 | 
  
   
CEE 
 | 
 
| 
   
42 
 | 
  
   
Workshops 
 | 
  
   
Sr.DME 
 | 
  
   
CWE 
 | 
 
| 
   
53 
 | 
  
   
Passenger amenities & other rly. User
  amenities 
 | 
  
   
Sr.DCM 
 | 
  
   
CCM 
 | 
 
IRPSM
@ DIVISIONAL LEVEL
Ø Creation of
“New Works” proposal with justification & Abstract Cost.
Ø Forward to
Finance (Sr.DFM) for vetting.
Ø Sanction of
Proposal  - by DRM (if within DRM powers)
Ø Forwarding
of proposals to Zonal Railway ( If beyond DRM’s powers)
Ø Adding all
the Works sanctioned under DRMs powers – to the list of “IN PROGRESS” works in
IRPSM.
Ø Assigned
unique Project ID as explained below. 
Ø Reporting
of status every month for each work by respective Exexutive Agency.
Ø Generation
& Printing (if desired only) of Works Programme reports.
IRPSM
@ ZONAL RAILWAY LEVEL
Ø Examination
and processing of “New Works” proposals as received from Divisions will be
forwarded by CPDE – Chief Planning & Designs Engineer the respective Zonal
Plan Head Co ordinators.
Ø Creation of
“New Works” proposals.
Ø Forward to
Finance (FA&CAO) for vetting.
Ø The vetted
proposals forwarded by Plan Head Co ordinators will be checked and then
forwarded to GM through PCE for Sanction.
Ø Sanction of
Proposal  - by GM (if within GM powers)
Ø Forwarding
of proposals to Railway Board ( If beyond GMpowers)
Ø Adding all
the Works sanctioned under GM powers – to the list of “IN PROGRESS” works in
IRPSM.
Ø Assigned
unique Project ID as explained below. 
Ø Defining
Funds availability & Sanction limits for Zonal Railway HQ & Divisions.
Ø Reporting
of status every month for each work by respective Exexutive Agency.
Ø Generation
& Printing (if desired only) of Works Programme reports.
IRPSM
@ Railway Board Level
Ø Forwarding
of proposals received from Zonal Railways by EDCE(G) to Nodal Directorates for
respective Plan Heads.
Ø On line
shortlisting, Recommedning& Forwarding to EDCE(G) 
Ø Above 5
Crores each -  Proposals forwarded by
Nodal Directorates to EDF(X) – I & II for Finance Concurrence.
Ø Below 5
Crores each – Online shortlisting, recommending & forwarding to EDCE(G) by
Nodal Directorates through concerned AMs (Additional Members) for Plan Heads.
Ø Compilation
of all shortlisted proposals (Below 5 Crores each) by EDCE(G) for meeting of
AM’s committee
Ø At any
time, ON LINE YELLOW SLIP
can be attached on-line and file can be moved out of the normal path for
consultation.  All yellow slip communications
will be kept off the general record.provision for the off-the-record
consultation on Proposals.
Ø Such
shortlisted & recommended proposals for each Plan Head with On line consent
and remarks of Finance will be processed by Nodal Directorates through EDCE(G)
on the file for approval of Board &Honorable Minister
for Railways.
Ø Assigned
unique Project ID as explained below. 
UNIQUE
PROJECT ID  - 14 DIGIT
| 
   
1 
 | 
  
   
2 
 | 
  
   
3 
 | 
  
   
4 
 | 
  
   
5 
 | 
  
   
6 
 | 
  
   
7 
 | 
  
   
8 
 | 
  
   
9 
 | 
  
   
10 
 | 
  
   
11 
 | 
  
   
12 
 | 
  
   
13 
 | 
  
   
14 
 | 
 
| 
   
Zonal Rly 
 | 
  
   
Division 
 | 
  
   
Plan Head 
 | 
  
   
Year of sanction 
 | 
  
   
Authority sanctioned (like
  GM,DRM etc) 
 | 
  
   
Executing Agency (Like Sr.DEN
  or Sr.DOM) 
 | 
  
   
Serial Number 
 | 
 |||||||
UNIQUE
PROJECT ID  - 14 DIGIT  - 
an
example of Passenger Amenities Work (Plan Head 51) Sanctioned by GM in Mumbai
Division of Central Railway
| 
   
0 
 | 
  
   
1 
 | 
  
   
0 
 | 
  
   
2 
 | 
  
   
5 
 | 
  
   
1 
 | 
  
   
1 
 | 
  
   
6 
 | 
  
   
3 
 | 
  
   
0 
 | 
  
   
0 
 | 
  
   
0 
 | 
  
   
0 
 | 
  
   
7 
 | 
 
| 
   
Central Railway 
 | 
  
   
Mumbai Division 
 | 
  
   
Plan Head 
 | 
  
   
2016-17 
 | 
  
   
GM 
 | 
  
   
Not identified 
 | 
  
   
Serial Number 
 | 
 |||||||
Hence
Project ID for the above work is “01025116300007”
ADVANTAGES
OF IRPSM
Ø
A paperless
office .  All files will move online
without involvement of physical files.
Ø
Completely
reduce transit time of file from one office to another.  Proposals reach Boards office within no time.
Ø
All
requisite justification, plans, drawings, sanctions and permissions will be
attached to the proposals.
Ø
Online
monitoring the work in progress of all the works.
No comments: