Zone Works
·        
Source: 1203E, 1208E, 1209E
·        
Meaning:  Works of ordinary repairs & maintenance,
petty nature works of a particular zone ( Like SCR) or Area ((say Secunderabad)
·        
Piece work contract is
adopted for Zone works.  Only unit rates fixed, without
reference either to total quantity of work/material supplied. 
·        
Advantageous
to allot all minor works & all works of repairs & maintenance in a particular zone
for a definite period to one Contractor. 
Works under Zone Contracts - (Revenue
only) 
1.      
Additions/alterations
to the existing structures, special repair works, supply of building materials
- But each
work / Work order not exceeding Rs.5 Lakhs. 
2.      
All
ordinary repairs & maintenance works 
3.      
Supply
of materials. e.g., bricks, lime, sand etc which are likely to be required in a
Zone during the year.
·        
 Period – one year- Normally 1st July to 30th
June. 
·        
Period
may be extended more than a year with the concurrence of Accounts, if it is
advantageous to Railways.
·        
Ensure
all works of old contract are completed by 30th June. 
***