MCQ on GCC for Services
By Nageswara Rao, 9492432160
Clickfor Revised GCC for Services
Click for PDF document i.e., MCQ on GCC for Services
1.GCC for Services
issued in the year ?
- 2020
- 2019
- 2018
- 2017
2.Which is not an
example of Service Contract
- Publicity on Platforms / Trains
- Maintenance, Housekeeping areas
- Professional, Intellectual, Training areas
- Consultancy & Advisory services
3.QCBS stands for
______________________
- Quality & Cost Based Standards
- Quality & Contract Based Selection
- Quotation & Cost Based Selection
- Quality & Cost Based Selection
4.Two Packet system
of bidding in Service Contracts applicable for valuing _______ and above
- Rs. 10 Crores
- Rs. 50 Lakhs
- Rs. 5 Crores
- Rs. 1 Crore
5.Which of the
following is incorrect in regard JV - Joint Ventures / Consortium in Service
Contracts
- Lead Member shall have majority (at least 51 % ) share
- Other Members shall have a share of not less than 20 %
each , if JV firms with up to 3 Members
- Other Members shall have a share of not less than 12 %
each , if JV firms with more than 3 Members
- If JV firm with Foreign Member (s), the lead Member has
to be an Indian Firm
6.Choose the
incorrect one - QCBS method adopted in Service Contracts
- Applicable for All Service Contracts
- The bid with highest weighted combined score (Quality
& Cost) shall be selected
- The weightage of the technical parameters i.e.,
non-financial parameters in no case should exceed 80 %
- Applicable for Service contracts having bid value
exceeding Rs. 50 Lakhs
7.In an example of
Service Tenders, A quoted Rs.80, B quoted Rs. 90 and C Quoted Rs.100, what is
financial score of Mr C (formulae=LFB / F x 100) LFB stands for Lowest
Financial Bid & F stands for Quoted Amount
- 125
- 80
- 100
- 120
8.Work Experience:
Should have satisfactorily completed, in the last three financial years and
current FY upto the date of opening of Tender, One similar single service
contract for a minimum of ____ of the advertised value of bid.
- 35
- 50
- 150
- 60
9.Financial Turn
Over Should have aggregate turn over not less than _______of advertised bid
value during the last three financial years and current year up to the date of
opening of Tender
- 35
- 50
- 150
- 60
10.Bidder should
have access to or has available liquid assets, line of credit and other
financial means to meet cash flow that is valued _____ estimated bid value net
of applicants other contractual commitments.
- 10 %
- 5 %
- 50 %
- 20 %
11.If two or more
offers are lowest and same: bidder with max bid marks will be considered
lowest. If Bid marks also same- ________________will be considered.
- Higher cumulative annual financial turn over the past
three FY and current year
- Highest liquidity
- Higher cumulative completed similar works over the past
three FY and current year
- Highest score of Technical Bid
12.EMD - For
services are estimated to cost up to Rs. 1 Crore is _____ of the estimated cost
of the work
- 20 %
- 5 %
- 10 %
- None of the above
13.Execution of
Agreement - Within______ after the receipt of communication that the agreement
is ready
- 14 days
- 90 days
- 7 days
- 30 days
14.Contract
document / Agreement shall be prepared and signed by the both parties in ______
and given to ____________
- 3 copies , Finance, Executive & Contractor
- 2 copies , Executive & Contractor
- 2 copies, Finance & Contractor
- 4 copies, Finance, Executive, Audit & Contractor
15.There is no
provision of Security Deposit in the Service Contracts. Am I ____
- Serious
- Joking
16. Performance
guarantee at a rate of _______ of the contractual value shall be deposited by
the successful bidder
- 5 %
- 20 %
- 2 %
- 10 %
17.In case the
contractor fails to submit the requisite PG even after ______ from the date of
issue of LOA, the contract shall be terminated duly forfeiting EMD and other
dues, if any payable against that contract.
- 60 days
- 90 days
- 30 days
- 120 days
18.Penal interest
of _______ shall be charged for the delay beyond 30 days and up to the date of
submission of PG from the date of issue of LOA
- 15 % per annum
- 12 % per annum
- 10 % per annum
- 8 % per annum
19.Services - EMD
is exempted for _____________
- MSEs (Micro & Small Enterprises) recognized by
Ministry of MSME (Micro, Small & Medium Enterprises)
- Startups recognized by DIPP (Department of Industrial
policy & Promotion )
- Both of the above
- None of the above
20.Services - The Earnest
Money Deposit shall be rounded to the nearest _____
- Rs. 100
- Rs.5
- Rs. 10
- Re 1
21.Services - If
the value of Contract decreases by more than 25% of the original contract value,
______________________________
- PG amounting to 5 % of the decrease in the contract
value shall be returned to contractor.
- PG amounting to 10% of the decrease in the contract
value shall be returned to contractor.
- Performance guarantee amounting to 10% of the decrease
in the contract value shall be adjusted as Security Deposit
- Performance guarantee amounting to 10% of the decrease
in the contract value shall not be returned to contractor.
22.If the penalty
imposed exceeds 50% or 75 % of the applicable maximum penalty, a PG equivalent
to _______ & ____________ respectively of the applicable PG shall be
forfeited.
- 25 % and 50 %
- 50 % and 75 %
- Nil and 25 %
- 30 % and 60 %
23.PG shall be
initially valid up to the stipulated date of completion and maintenance period,
if any plus ________ beyond that.
- 90 days
- 120 days
- 60 days
- Nil
24.What is the
object of Performance Guarantee in Service Tenders ?
- The balance work shall be got done independently
without risk & cost of failed contractor.
- To keep the offer open till the finalization of Tender
- Replacement of Security Deposit
- None of the above
25.Whenever the
Contractor (in Services) is rescinded, the failed contractor shall be debarred
for a period of _____ years from the date of rescindment from participating
from the bids.
- 2 years , but can participate in the bid of balance of
services of failed contractor
- 1 year , but can participate in the bid of balance of
services of failed contractor
- 2 years , and not eligible to participate in the bid of
balance of services of failed contractor
- 1 year , but can participate in the bid of balance of
services of failed contractor
26.Liquidated
Damages - For delayed on part of Contractor, a penalty a sum of equivalent of
_______ of the contract value of the service of each ______ or part of the
_______
- 0.10 % , week
- 1 % , week
- 0.40 %, month
- 0.50 %, month
27.Total amount of
LD (Liquidated Damages) shall not exceed _____ of the Contract value --
Services
- 10 %
- 2 %
- 20 %
- 5 %
28.Operation of an
item by more than 125 % of the Agreement Quantity needs the approval of
__________
- Officer of the rank not less than JAG and Finance
concurrence required
- Officer of the rank not less than HAG and Finance
concurrence required
- Officer of the rank not less than SAG without Finance
concurrence
- Officer of the rank not less than SAG and Finance concurrence
required
29.Services -
Variation beyond 150 % - individual item - subject to __________
- Prohibited
- permitted in exceptional unavoidable circumstances with
associated finance concurrence and paid at 96 % of the rate
- permitted in exceptional unavoidable circumstances and
paid at 96 % of the rate. Finance Concurrence not required
- permitted in exceptional unavoidable circumstances with
associated finance concurrence and paid at 94 % of the rate
30.Services -
Variation beyond 150 % of the overall Agreement value - subject to
- Normally should not be permitted and if found
necessary, either fresh tenders or negotiating with existing tenderer.
Concurrence of PFA / FA&CAO (C) and approval of PHOD
- Normally should not be permitted and if found
necessary, either fresh tenders or negotiating with existing tenderer.
Personal concurrence of PFA / FA&CAO (C) and approval of GM
- Normally should not be permitted and if found
necessary, through fresh tenders. Personal concurrence of PFA / FA&CAO
(C) and approval of GM
- Normally should not be permitted and if found
necessary, either fresh tenders or negotiating with existing tenderer.
Associated Finance concurrence and approval of GM
31.Variation in
Service Contracts - Decrease beyond 25 % for individual items or overall
agreement value. Subject to ?
- Approval of an Officer not less than rank of SAG,
Finance Concurrence not required obtaining "No claim
certificate" from Contractor
- Approval of an Officer not less than rank of PHOD,
Associate Finance Concurrence, obtaining "No claim certificate"
from Contractor
- Approval of an Officer not less than rank of SAG,
Associate Finance Concurrence, obtaining "No claim certificate"
from Contractor & obtaining "No Dues Certificate" from the
Executive
- Approval of an Officer not less than rank of SAG,
Associate Finance Concurrence, obtaining "No claim certificate"
from Contractor
32.The limit for
varying quantities for minor value items shall be 100% . A minor value item for
this purpose is defined as an item whose original agreement value is less than
_____ of the total original agreement value.
- 10 %
- 1 %
- 5 %
- 20 %
33.Services - If
Vitiation happens, _____________
- Obtain the Sanction of the Officer as per Single Tender
- Obtain the Sanction of the Officer as per Single Tender
with personal Finance Concurrence of PFA / FA&CAO(C)
- Payment shall be restricted to the lowest calculated
value of all valid offers
- None of these
34.Services -
Payments to Contractors shall be rounded off to the nearest ________
- Rupee
- 5 Rupees
- 10 Rupees
- 100 Rupees
35.Service
Contracts - The amount payable on account of Price variation shall be settled
every ______
- Quarter
- Month
- No such duration. As and when the bill is submitted.
- 15 days
36.Service
Contracts - PVC (Price Variation Clause) for Contracts whose delivery period
extends beyond _________
- 6 months
- 12 months
- 24 months
- None of these
37.Services - The
Base Month for PVC shall be taken as ________________ unless otherwise stated
elsewhere.
- Previous month to the month of opening of bids
including extensions, if any,
- month of opening of bids including extensions, if any,
- Month next to the month of opening of bids including
extensions, if any,
- None of the above
38.Services
Contracts - for calculation of PVC - Fixed component is always _______
- 10 %
- 20 %
- 15 %
- 30 %
39.PG Shall submit
in __________ within 30 days from LOA Issued date
- 2 separate parts of 5 % each
- 5 separate parts of 2 % each
- 1 part of 10 %
- 4 separate parts of 2.5% each
40.Service
Contracts - For determination, rly to issue “performance notice” in a
prescribed format, “________notice” and finally “Termination Notice”
- 14 days
- 7 days
- One month
- None of the above
41.Service Tenders
- Minus rates quoted
- Permitted, but double the PG to be submitted in case of
allotted work
- Bidders shall not quote minus rates— If at all quote, his
EMD to be forfeited
- Bidders shall quote minus rates, but not consider for
evaluation of Tenders—EMD to be returned.
- None of the above
42.Services -
Tendering through ________
- GeM
- IREPS
- e Tendering
- E RA
43.Service Tenders
- EMD -For services estimated to cost more than Rs. 1 crore
- Rs. 2 lakh plus 1/2 % (half %) of the excess of the
estimated cost of work beyond Rs.l crore subject to a maximum of Rs 1
crore
- Rs. 2 lakh plus 1/2 % (half %) of the excess of the
estimated cost of work beyond Rs.l crore subject to a maximum of Rs 5
crore
- Rs. 2 lakh plus 1% of the excess of the estimated cost
of work beyond Rs.l crore subject to a maximum of Rs 1 crore
- Rs. 2 lakh plus 1 % of the excess of the estimated cost
of work beyond Rs.l crore subject to a maximum of Rs 5 crore
Answers
for MCQ on GCC for Services
QN
|
Answer
|
|
QN
|
Answer
|
|
QN
|
Answer
|
|
QN
|
Answer
|
|
QN
|
Answer
|
1
|
C
|
|
11
|
A
|
|
21
|
B
|
|
31
|
D
|
|
41
|
B
|
2
|
A (It is a Earning contract)
|
|
12
|
D (2 %)
|
|
22
|
A
|
|
32
|
B
|
|
42
|
A
|
3
|
D
|
|
13
|
C
|
|
23
|
C
|
|
33
|
C
|
|
43
|
A
|
4
|
B
|
|
14
|
A
|
|
24
|
A
|
|
34
|
A
|
|
|
|
5
|
C (Correct one is 10 %)
|
|
15
|
A
|
|
25
|
C
|
|
35
|
A
|
|
|
|
6
|
A
|
|
16
|
D
|
|
26
|
A
|
|
36
|
D (18 Months)
|
|
|
|
7
|
B
|
|
17
|
B
|
|
27
|
D
|
|
37
|
B
|
|
|
|
8
|
A
|
|
18
|
A
|
|
28
|
C
|
|
38
|
C
|
|
|
|
9
|
C
|
|
19
|
B
|
|
29
|
B
|
|
39
|
D
|
|
|
|
10
|
B
|
|
20
|
C
|
|
30
|
B
|
|
40
|
B
|
|
|
|
****