Railway Accounts Department Examinations

Showing posts with label Works Contracts. Show all posts
Showing posts with label Works Contracts. Show all posts

Monday, March 16, 2026

PG & APG in Works - Simple Calculation


Click for ACS 11 (introduction of APG)

 PG & APG in Works - Simple calculation 

95 is the safety line; below it APG joins

Example: Advertised Tender value = Rs. 100


Successful Bidder’s offer is 

PG

APG

Total PG 

Rs. 95 & above

5 %

Nil

5 %

Below Rs. 95

5 %

5 %

10 %


Authority: New Para 16 (4) (h) of Part II of IR Standard GCC - General Conditions of Contract for Works April 2022 Edition vide ACS 11 vide Railway Board Letter dated 13.03.2026


PG stands for Performance Guarantee & APG stands for Additional Performance Guarantee


PG & APG are calculated on the Original Contract Value (Accepted Bid Value), not on Advertised Tender Value.

95 or above → Only PG (5%)

Below 95 → PG (5%) + APG (5%)  







































































Saturday, March 14, 2026

GCC for Works 2022 April - Correction Slip - ACS 11 of March, 2026

 




Click for ACS 11 to GCC for Works 2022 April


ACS No. 11 to the Indian Railways Standard General Conditions of Contract (GCC), April-2022, issued by Railway Board on 13-03-2026 and applicable prospectively to Works Contracts of Indian Railways.

Below is the item-wise explanation, clearly indicating what existed earlier and what is newly modified.


1. Bid Security (Para 5(1)(a) – Part-I of GCC-2022)

Existing Provision

Earlier, Bid Security depended on the value of the work. If the estimated cost of work was up to ₹1 crore, the bidder had to submit 2% of the estimated cost as Bid Security. For works above ₹1 crore, the Bid Security was calculated as ₹2 lakh plus 0.5% of the amount exceeding ₹1 crore, subject to a maximum limit of ₹1 crore.

Modified Provision

The revised rule simplifies the structure. For all works, irrespective of value, Bid Security will be 2% of the estimated cost of the work. The complicated formula linked to the ₹1 crore threshold has been removed.

Other Provisions (unchanged but reiterated)

  • Bid Security must be rounded off to the nearest ₹100.

  • Start-ups recognised by DIPP (Department for Promotion of Industry and Internal Trade) are exempt from Bid Security.

  • Labour Cooperative Societies need to submit only 50% of the Bid Security.


2. Sub-contracting Limit (Para 7(a)(i) – Part-II of GCC-2022)

Existing Provision

Earlier, the rule stated that the total value of work assigned to sub-contractors should not exceed 50% of the total contract value.

Modified Provision

The rule is now made stricter and more structured.

  • Sub-contracting is limited to a maximum of 40% of the contract price.

  • The contractor must execute at least 60% of the contract value directly under its own supervision and personnel.

Additionally, the revised provision clarifies that procurement of materials, hire of equipment, or engagement of labour by the contractor will not be treated as sub-contracting.


3. Performance Guarantee (Para 16(4) – Part-II of GCC-2022)

Existing Provision

Earlier, the successful bidder had to submit Performance Guarantee equal to 5% of the original contract value. One of the forms permitted was an Insurance Surety Bond, but this option was allowed only when the Date of Completion (DOC) was within 36 months. If the completion period exceeded 36 months, another form of security had to be submitted.

Modified Provision

The revised rule retains 5% Performance Guarantee, but adds important clarifications:

  • Additional Performance Guarantee may also be required as per clause 16(4)(h).

  • If the Date of Completion is extended, the contractor must submit extended Insurance Surety Bond / fresh Insurance Surety Bond / fresh Performance Security before expiry of the existing bond.

Thus, the emphasis is now on continuity and validity of security during extensions of contract period.


4. New Clause – Additional Performance Security for Abnormally Low Bids (Para 16(4)(h))

Earlier Position

There was no explicit clause dealing with additional security when a bidder quoted unusually low rates.

New Provision

A new rule has been introduced.

If a bid is accepted at rates below the advertised tender value, the bidder must submit Additional Performance Guarantee (APG).

Structure of APG:

  • Bid quoted between 0% to 5% below advertised value → No additional security

  • Bid quoted more than 5% below advertised value → Additional Performance Guarantee of 5%

This provision is intended to discourage abnormally low bids and protect project execution risk.


5. Bid Capacity Eligibility (Annexure VI)

Existing Provision

Earlier, this rule applied only to tenders with advertised value above ₹20 crore. In such cases, bidders were required to demonstrate available bid capacity equal to or greater than the bid value.

Modified Provision

The threshold has been reduced from ₹20 crore to ₹10 crore.

Now, for tenders above ₹10 crore, bidders must prove available bid capacity equal to or greater than the tender value.

This change expands the financial capacity check to a larger number of works contracts.


6. Illegal Gratification / Ethical Practices (Para 18(1))

Existing Provision

Earlier, the clause simply stated that if the contractor offered bribes, commissions, gifts, or undue advantage to Railway officials, the contract could be rescinded and losses recovered.

Modified Provision

The rule has been expanded into a detailed “Code of Integrity in Procurement” covering several prohibited practices. These include:

  • Corrupt Practice – offering or accepting bribes or rewards.

  • Fraudulent Practice – false information or misrepresentation in tendering.

  • Anti-competitive Practice – bid rigging, cartelization, or collusion.

  • Coercive Practice – threats or pressure affecting procurement decisions.

  • Conflict of Interest – relationships affecting impartial decision-making.

  • Undue Advantage – misuse of confidential information.

  • Obstructive Practice – interfering with investigation or audit.

This significantly strengthens procurement ethics and transparency provisions.


7. Punitive Provisions for Violation of Code of Integrity (Para 18(2))

Existing Provision

Previously, the rule mainly stated that if the contractor had monetary dealings with Railway employees, the Railway could cancel the contract and recover losses.

Modified Provision

The revised rule introduces detailed punitive measures if integrity violations are detected.

Possible actions include:

  • Forfeiture of Bid Security

  • Cancellation of contract

  • Recovery of payments including advances with interest

  • Debarment or banning from future tenders for at least one year

  • Reference to Competition Commission of India in anti-competitive cases

  • Initiation of disciplinary or criminal proceedings

This converts the earlier clause into a comprehensive penalty framework for procurement misconduct.


In summary, the Correction Slip mainly introduces:

  • Simplified Bid Security rule (2% for all works)

  • Stricter limits on sub-contracting (40%)

  • Provision for Additional Performance Security for low bids

  • Lower threshold for bid capacity check (₹10 crore)

  • Detailed integrity and anti-corruption provisions with penalties





Tuesday, December 30, 2025

Types of Contracts - Works, Services & Stores - Definitions & Differences



Tenders & Contracts: Differences between Services, Works & Stores


Services → Skill or expertise hired - Any subject matter of procurement otherthan Goods or Works   - Skill


Works → Construction or execution as per drawings - The work contemplated for delivery of services as per drawings & schedules set forth in the Bid forms & required to be executed according to the specifications. - Structure


Goods / Stores → Physical items purchased and ownership transferred - Contract for sale of goods is a Contract whereby the seller transfers or agrees to transfer teh property in goods to the buyer for a price. - Supply


Our Channel (for study material)

  MCQ WhatsApp Channel



Sunday, September 15, 2024

Works Tenders - Types of

 

Tenders in Works  – Types


  1. Open Tenders or Advertised tenders.

  2. Limited

  3. Special Limited tenders.

  4. Single Tender.


  1. Open/Advertised tenders:




ü  Open tendering system is the widely used one as it ensures fair competition by which reasonable rates can be obtained.  The system of invitation to tender by public advertisement in the most open and transparent  manner possible should be used as a general rule and must be adopted.  Powers to invite Open tenders Vide item No.6 of part-A of MSOP.


ü    Powers have been delegated to officers at different levels to call open tenders. 


ü  Generally before calling tenders, vetted sanctioned estimate for the work proposed to be tendered for, should be available and also other requirements such as funds availability, approved drawings, site availability, materials to be issued by Deptt etc., .   In the absence of sanction of detailed estimate, pre-vetting of tender schedule is to be taken.


  1. Limited tenders: 


ü  Where for reasons which should be in the public interest, it is considered not practical or advantageous to call for open tenders, Limited tenders may be invited with the concurrence of FA&CAO and approval of competent authority


ü   Limited tenders are to be invited from contractors borne on approved list. 


ü  In S.C.Rly, PHOD/CHOD is having powers to call Limited tenders up to Rs.5 crores in each case, HOD/DRM/ADRM/CSM is having powers up to Rs.1 crore. JAG officers have powers to call LT up to Rs.25 lakhs.  At least 10 names should be on the approved list of contractors.

  1. Special Limited tenders:


     

ü  This type of tendering system is adopted for works of specialized nature, works of urgent nature and consultancy works.  Finance concurrence is necessary. 


ü Special LT will be invited from the specialized and reputed contractors/organizations/agencies.


ü   Tenders from whom Special LT are to be invited should preferably be more than six but not less than four. 


ü  Tenderers need not be borne on the approved list.


  1. Single tender: 


ü  Single tender is invited in case of emergencies, accidents, breaches involving dislocation to traffic. 


ü  The powers to be exercised in times of cyclone, floods, accidents, sabotage, enemy action, explosions, cases of extreme urgency such as works or supplies necessary to safeguard life or property or repair damage to track caused by flood breaches,  washaways, accidents or other unforeseen contingency so as to maintain through communication.


ü   For restoration of traffic within shortest possible time, single tender is invited from the experienced and reputed contractor who has the previous experience of having executed such emergency works. 


ü   CAO/Con is having full powers to call single tender in case of works of specialized nature only.


ü   Finance concurrence is necessary. Estimate provision should be available to meet the expenditure incurred through quotation route. 


ü  To dispense with calling of tenders for works which are urgent in nature and to accept offers received in response to quotations. Finance concurrence is necessary. Powers have been delegated in Item No.5 – F of part – A of MSOP- works matters. 


ü  The powers shall be exercised by the officers with their administrative approval.  The powers should be exercised sparingly. The circumstances under which quotations have to be called should be spelt out. Quotations should not be for items which can be executed through the existing contracts including zonal contracts. Quotations should not be for fancy items. After finalization of the quotations, work order will be placed on the selected bidder. 

&&&&&&


Thursday, December 7, 2023

Works Contracts - Types

 

 

 

Works Contracts - Types 

 

Lump Sum Contracts: 



  • A contract under which the contractor engages to carry out a work or effect supply as specified and within a given period for a fixed total sum;



  • His receipt of this sum being dependent on his completing the work or supply to specification and time, irrespective of the actual quantities and kind of work done or materials supplied in achieving his result. 

  

  • In case of departure from the work or supply as specified  - Reduction from the consideration may be made at the discretion of the Competent authority for failure on the part of the Contractor. 

 

In simple: 



  • Fixed Total sum - To be paid to the Contractor. 
  • Complete the Work / Supply to the specification. 
  • Within a given period.  
  • Not relevant: Actual quantities of work or material supplied.   
  • Suitable for Contracts like Construction of 100 Nos of Type I Quarters, Replacement of wiring in 200 Type I Quarters, etc.

 



Schedule Contract: 



  • It is simplest form of Contract 



  • The contractor engages to carry out a work or effect supply as specified and within a given period at fixed unit rates or prices for each of the various items comprising such work or supply,



  • the sum he is to receive depending on the actual quantities and kinds or work done or materials supplied in completing the work or supply to specification and time.  

 

  • It is not repugnant to the above definition to show in such contracts the approximate amount of the contract, based on approximate quantities and the fixed unit rates.   
  •  

 

In simple: 



  • The sum paid to the Contractor  - Depends on the actual Quantities of work or material supplied 
  • Fixed unit rates or prices for each of the various items (Not Total work value)  
  • Within a given period as per specifications.  
  • Contract rates and quantity of various activities are fixed beforehand at the time of the award the Work. 
  • Most commonly used type of Contract in Indian Railways.  
  • No lump sum payment is permitted except in Earth work. 

 

Piece Work Contracts: 



  • A contract under which only unit rates or prices for various kinds of work or materials are agreed upon,
  • without reference either to the total quantity of work to be done or material supplied; 
  • The Railway may indicate its intention as to the maximum value of the orders it is likely to place;
  • but the contractor cannot claim to be given an order for more than one unit of work or supply. 
  • After the contract is executed, specific orders for work or supply may be placed against it. Maximum value of One Work Order is Rs.5 Lakhs 
  • The rate of progress may not be specified;
  • but if it is not satisfactory the contract can be terminated. 

In Simple: 



  • Agreed only unit rates or prices for various kinds of works / materials 
  • No reference of Total work to be done  or  Materials to be supplied. 
  • Railways indicate maximum value of work to be executed or material to be supplied. But there is no guarantee. 
  • Contractor cannot be claimed to be given for more than one order. 
  • After the contract is executed, specific orders for work or supply may be placed against it. 
  • Maximum value of One Work Order is Rs.5 Lakhs  
  •  Also called Fixed Rate Contracts 
  • Generally Time period is One year. 

  

 

Example: Zonal Contracts