Railway Accounts Department Examinations

Showing posts with label GCC for Services. Show all posts
Showing posts with label GCC for Services. Show all posts

Friday, July 24, 2020

Differences between GCC of Works and Services

Inputs by Shri Afzaluddin, Sr.AFA/SCR

Differences between GCC of

SN

ITEM

WORKS

SERVICES

1

EMD rounded to

Rs. 100

Rs.10

2

EMD of successful tenderer

Retained as SD

Returned to the tenderer after submission and verification of prescribed PG (Because SD is not applicable)

3

EMD exemption

MSME & Start-ups registered with DIPP

Start-ups registered with DIPP only

4

PG - % of Contract value

5 %

10 %

5

Submission of PG

Within 21 days from LOA

Within 30 days from LOA

6

Penal interest for delayed PG

12 % from 22nd day to 60 days

10 % from 31st day to 90 days

7

Termination of Contract on failing of PG submission

After 60 days from LOA

After 90 days from LOA

8

SD

5%

Nil

9

LD – Liquidated Damages

0.5 % of 1 % of Contract value for each week or part of the week

Shall not exceed 5 % of Contract value plus token penalty

10

Forfeiture of PG

No link with LD

LD exceeds 50 % - 25 % of PG to be forfeited

LD exceeds 75 % - 50 % of PG to be forfeited

11

Vitiation

Sanction of Competent Authority as per Single Tender to be obtained.

However

1. up to 50 Lakhs – 10 % Vitiation permitted

2. Above 5 Lakhs – 5 % Vitiation permitted

 

Payment shall be restricted to the lowest calculated value of all valid offers

12

Two packet system

Above Rs. 10 Crores Tenders

Above Rs. 50 Lakhs tenders

13

PV Clause

Above Rs. 5 Crores

More than 18 months contract – irrespective of its value

14

PV clause

Labour component – 20 %

Labour component – 70 %

15

Technical eligibility

In the last 7 years

1 work – 60 % of value

2 works – 40 % of value (each)

3 works – 30 % of value (each)

In the last 3 years

1 work – 35 % of value

16

Technical Eligibility

Rs. 50 Lakhs and above Tenders

All works

17

Bonus for early completion

1 % for every 30 days

Nil

18

Contractor’s Measurements

Above Rs. 20 Crores works

Not applicable

19

Tendering through

IREPS

GeM

20

GCC issued by

Civil Engineering Directorate

Transformation Cell ( Mech & EnHM Directorates)

21

GST

12 % on composite supply

18 % for services other than Goods/Works

 

&&&

Monday, November 4, 2019

GCC - General Conditions of Contract for Services


  • Railway Board releases New GCC - General Conditions of Contract for exclusively to Service Contracts.  
  • Till the date, GCC for Works is applicable for such Service Contracts. It is 106 pages document released in January, 2018.  However due to typographical mistakes, the same was revised and uploaded on 20.03.2018.
  • It helps to improve contract management, delivery of services and to reduce Government litigation, since Railways have entered more and more service contracts in non-operational areas such as cleaning, facilities management, consultancy etc.



Click below