Departmental Charges ( D&G Charges ) in Works
Estimates
- Sources:
1. Railway Board Letter No. 2022/E&R/3(2)/1 dated 28.12.2022 Click here
2. Railway Board Letter No.
2018/E&R/3(2)/1 dated 04.03.2020 Clickhere
3. Para 1120 of IR Engineering Code
- A committee was constituted at the Railway Board level to review the D&G charges thoroughly for various Works Estimates.
- Based
on the recommendations of the Committee, the following changes have been
affected vide letter under Source No. 1 above.
- Departmental
Charges - New term in place of D&G Charges
- D&G
Charges stands for Direction & General Charges
- Will
cover - Both i.e., Departmental manpower and Hired manpower of Projects
(including Revenue posts)
- Electrical
and S&T Works - Distinction of “With & Without Block” works
removed.
- Consists
of the Establishment portion only.
- Not
included: The cost of Pay & Allowances of Land Acquisition
Staff. Because the same is included in the Sub estimate of Land
Acquisition as part of the Project.
- Other than the Establishment portion -Removed. However, ERW & Sports Development Fund are continuing.
- Gazetted
posts - Not more than 50% of Departmental Charges should be utilised
% Ceiling of Departmental Charges for Various Works
|
Projects |
Percentage - Departmental Charges |
|
Civil Engineering |
5.33 % |
|
Track Renewal Works (Primary & Secondary) |
1.53 % |
|
Electrical Projects (incl: RE) |
7.16 % |
|
S & T |
10.05 % |
|
Mechanical |
4.93 % |
Note: Break up of the above percentages among various
Departments as per the Railway Board Letter dated 28.12.2020 (Annexure-II)
ERW:
- ERW
stands for Environmental Related Works
- 0.5
% provision of the overall value of the Estimate including Contingency
1%. (Example: If the Estimate value is Rs.100, the ERW provision is Re
0.50)
- Applicable
to Plan Heads 11, 14, 15, 30 & 42 only
- Not
applicable - If the works under the above Plan Heads are funded through
EBR(IF)
- EBR(IF)
stands for Extra Budgetary Resources (Institutional Finance)
- If
the work is specifically for Environment Management, it should be
processed for sanction as Itemised Work in Pink Book.
Sports Development Fund:
- Object:
To create a robust Sports infrastructure in tune with IR Sports
contribution
- 0.1
% provision of the overall value of the Estimate including Contingency
1%. (Example: If the Estimate value is Rs.100, the Sports Development Fund
provision is Re 0.10)
- Applicable
to all Plan Heads {Except Plan Heads 17 & 31 and Projects funded
through EBR(IF) }
- If
the work is specifically for Sports Development, it should be processed
for sanction as Itemised Work
Contingency:
- Uniform
1 % - shall be part of the Estimate. (Example if the
Total Estimate value is Rs.100, the provision of Contingency is Re. 1)
- Provision
for contingency - Should not be diverted to any new work or repair which
is not provided in the estimate. If so, it should require the
sanction of the authority who sanctioned the estimate. If the Sanctioned
authority is beyond GM, the GM Can sanction.
- The
contingency portion of Departmental charges is removed.
- Used
only for Unforeseen items essentially required for completing the
Project.
- Included:
Cost of Project specific training, if not covered in the Detailed
Estimate.
Example of Calculation of:
- The
Project Estimate Cost - Rs. 49500 (excluding Contingency). The
calculation of :
|
Item |
Calculated Amount |
Remarks |
|
Contingency |
Rs. 500 |
@ 1 % of the Estimate Value. Part of the
Estimate The calculation of Contingency is as follows: Value /100-1 x 1 49500 /99 x 1 = 500 That means Rs.500 is 1 % of Rs. 50,000 (overall value
of the Estimate) |
|
ERW |
Rs. 250 |
@ 0.5 % on the Total Estimate value.(incl:
Contingency) Worked out on the overall value of the Estimate including
Contingency i.e., 0.5 % on Rs.50000 |
|
Sports Development Fund |
Rs. 50 |
@ 0.1 % on the Total Estimate value.(incl:
Contingency) Worked out on the overall value of the Estimate including
Contingency i.e., 0.1 % on Rs.50000 |
Key points for MCQ
- Calculation
of the Contingency is Part of the Estimate, whereas ERW & Sports
Development Fund is on the overall value of the Estimate.
- Departmental
charges - New name of D&G charges
- D&G
charges stand for Direction & General charges
- Departmental
charges - Cover - Both Departmental Manpower and Hired Manpower including
Revenue posts.
- Consists
of the Establishment portion only. The non-Establishment portion was
removed.
- Gazetted
posts - Not more than 50%
- ERW
stands for Environmental Related Works
- Sports
Development Fund - 0.1 %, ERW - 0.5 %, and Contingency - 1 %
- ERW
and Sports Development Fund - Not applicable for Projects funded through
EBR(IF)
- EBR(IF)
stands for Extra Budgetary Resources (Institutional Finance)
- ERW
- Applicable to Plan Heads 11, 14, 15, 30 & 42 only.
- Sports
Development Fund - Applicable to all Plan Heads (except 17 & 31)
—--end—-