Grade Separator

 

Grade Separator

  • A Grade Separator is a structure that separates the levels of two intersecting transport routes.

  • In Railways and Roads, this includes:

    • Road Over Bridge (ROB) → Road goes above the railway track.

    • Road Under Bridge (RUB) → Road passes under the railway track.

    • Rail Flyover / Rail Over Rail Bridge → When one railway line passes above another.

  • Purpose: To ensure uninterrupted movement, improve safety, and allow higher speed operations.



  • Indian Railways achieved a milestone by conducting a 130 kmph trial run on one of Asia’s longest Grade Separator (Rail Flyover) at Katni, Madhya Pradesh.

  • This bridge demonstrates India’s engineering capabilities and supports modern high-speed railway infrastructure.

  • Grade separators help in decongesting busy junctions, especially where multiple railway lines cross.

  • They reduce accidents at level crossings, improve punctuality, and enhance track capacity utilization.

  • Katni is a vital junction linking routes to Delhi, Mumbai, Kolkata, and Chennai; the new flyover will make operations smoother and faster.


  • भारतीय रेलवे ने कटनी (मध्यप्रदेश) में एशिया के सबसे लंबे ग्रेड सेपरेटर (रेल फ्लाईओवर) पर 130 किमी प्रति घंटे की गति से सफल ट्रायल रन किया।

  • यह पुल भारत की इंजीनियरिंग क्षमता और आधुनिक रेलवे अवसंरचना का प्रमाण है।

  • ग्रेड सेपरेटर में –

    • रोड ओवर ब्रिज (ROB) – सड़क रेलवे लाइन के ऊपर से जाती है।

    • रोड अंडर ब्रिज (RUB) – सड़क रेलवे लाइन के नीचे से जाती है।

    • रेल फ्लाईओवर – एक रेलवे लाइन दूसरी के ऊपर से गुजरती है।

  • इनका मुख्य उद्देश्य है – सुरक्षा, समयबद्धता और ट्रेनों की तेज़ आवाजाही सुनिश्चित करना।

  • कटनी जंक्शन देश का प्रमुख रेल केंद्र है। नया ग्रेड सेपरेटर दिल्ली, मुंबई, कोलकाता और चेन्नई से जुड़ी लाइनों को अधिक सुगम और तेज़ बनाएगा।












Friday, May 10, 2024

RSP - Road Safety Projects - PH 30 - ROB / RUB - New Vertical

 

RSP - Road Safety Projects - PH 30 - ROB / RUB - New Vertical


  • Authority: Railway Board Letter No. 2024/CE-IV/ROB-RUB/SCR, WR, ECR & NR dated 07.05.2024


  • Object of New Vertical: Execution of ROBs/ RUBs has not kept pace with the pace of new sanctions being given.  

 

  • New Vertical   - CAO/Con/RSP  - Exclusively for Road Safety Projects - for Road Crossing Works i.e., PH 29 - Level Crossings and PH 30 - ROB / RUB

 

  • RSP stands for Road Safety Projects (RSP also Rolling Stock Programme) 

 

Salient features of RSP:

 

  • RSP vertical - headed by CAO/Con/RSP  who is in HAG - Higher Administrative Grade

 

  • Assisted by SAG/Engineering Dept, other officers and staff

 

  • Reporting directly to GM  

 

  • Associated Finance: FA&CAO/Con 

  

  • GC - General Consultant:  engaged by CAO/Con/RSP for holistic planning of RSP works incl: Feasibility studies (new name for Surveys), DPR preparation, Sanction of Work, detailed structural design, detailed estimate & engagement of PSSA/PMS/PMC

 

  • EPC / Hybrid mode EPC / BOQ based Contracts - for execution of RSP

 

  • Nodal Directorate for RSP :  Bridge Directorate in Railway Board  

 

  • CAO/Con/RSP: Execution in-charge of RSP 


  •  CAO/Con/RSP & his Officers will exercise the powers of Construction organisation as per MSOP  (in respect of all Technical, Financial, Contractual & Personnel matters)

 

  • PCE: Monitoring and overall coordination for RSP 

Key points of RSP: 


  1. RSP - New Vertical for PH 30 - ROB / RUB 

  2. RSP headed by HAG Officer (of Engineering Dept)  

  3. Reporting directly to GM 

  4. Associated Finance: FA&CAO/Con

  5. Nodal Directorate: Bridge Directorate (in Railway Board) 

  6. PCE: Overall coordination of RSP


Abbreviations: 


  1. RSP - Road Safety Works  

  2. RSP - Rolling Stock Programme 

  3. ROB - Road Over Bridge 

  4. RUB - Road Under Bridge

  5. CAO - Chief Administrative Officer (HAG rank) 

  6. HAG - Higher Administrative Grade (PHOD rank) 

  7. PHOD - Principal Head Of Department (HAG rank) 

  8. PCE - Principal Chief Engineer (HAG rank/PHOD) 

  9. SAG - Senior Administrative Grade 

  10. GC - General Consultant 

  11.  DPR - Detailed Project Report 

  12. PSSA - Project Supervision Services Agency

  13. PMS - Project Management System 

  14. PMC - Project Management Consultancy

  15. EPC - Engineering Procurement & Construction

  16. BOQ - Bill Of Quantities

  17. MSOP - Model Schedule Of Powers 

&&&&