Additional PG - Performance Guarantee calculation -If the Tenderer offered lower than the Tender Value

 Additional Meaning - YouTube

Additional PG calculation

If the Tenderer offered lower than the Tender Value

 

 

excerpt of Para 16 (4) (h) of Revised GCC for Works-July 2020  Click for Revised GCC 2020

 

 

"The tenderer who has offered lower total cost as compared to tender value by more than 10 %, shall be required to submit additional Performance Guarantee of value equal to half the percentage of tender value by which offer is lower than 10%. (e.g. in a tender costing Rs 100, if contract value is Rs 80, additional Performance Guarantee shall be [0.5x{(100-80)-10}] percentage of tender value.)"

 

 

Object : To discourage the Contractors to quote the unreasonable rates and doing incomplete  work  or abandon the work after awarding the same, because of non viable/non feasible rates.

 

Example A:

Tender value is Rs 100.  Tenderer offered rate is Rs 80 only. So calculation of PG is as follows:

 

PG Rate on Contract/Tender Value

Calculation

PG Amt

(Rs)

Original PG

5% of Contract Value Rs. 80

5/100x80

4.00

Additional PG

0.5 % of 10 i.e., {(100-80)-10} (additional

Performance  Guarantee of value equal

 to half the percentage of  tender value

by which offer is lower than 10%.

0.5/100x10

0.05

Total PG

 

 

4.05

 

Example B:

Tender value is Rs 100.  Tenderer offered rate is Rs 70 only. So calculation of PG is as follows:

 

PG Rate on Contract/Tender Value

Calculation

PG Amt

(Rs)

Original PG

5% of Contract Value Rs. 70

5/100x70

3.50

Additional PG

0.5 % of 20 i.e., {(100-70)-10} (additional

Performance  Guarantee of value equal

 to half the percentage of tender value

by which offer is lower than 10%.

0.5/100x20

0.10

Total PG

 

 

3.60

 

In Simple , calculation of Additional PG is 0.5 % of  (90 % of Tender Value - Accepted Offer value)

Note:

If the Lowest quote is Rs. 90 and above against Tender Value of Rs. 100, the PG is just 5 % of Contract Value only.

&&&&