Out of Turn Works - OOT Works
(many
times asked. Very important question for GRP & General expenditure optional)
ü Definition:  Works that are to be undertaken during a year,
provided neither provided in the Sanctioned works in the current year, nor
included in the Sanctioned works of Previous years. 
ü  Execution authority - should justify the need
to undertake the work immediately (though not included in the Sanctioned works)
and also why it could not be anticipated/included in the Pink Book/LAW.
ü Funds should be provided for OOT works - duly re appropriated within
the same Plan Head from the Itemized works.
ü CPDE
- Chief Planning and Design Engineer  
/   CE/P&D - Chief
Engineer/Planning & Design  - Nodal
officer for OOT works in a Zonal Railway. 
ü Prior
Finance Concurrence of PFA/Sr.DFM is required for OOT works in Zonal Railway
& Division respectively.  
ü  Passenger Amenities works :-
1.   Emphasis
/ Importance should be on creation of amenities of durable and lasting nature. 
2.    Funds should not be frittered / wasted on
provision of superficial items like furnishings & furniture etc. 
ü Funds
provided for OOT woks should be duly re appropriated within the same Plan Head
from itemized works. 
ü Safety works under OOT - Should be completed within a maximum period
of 8 months from the date of sanction of Detailed Estimate.  Otherwise, the object of OOT for safety works
itself is defeated. 
ü Before
obtaining Out of turn sanction of GM for traffic facilities/ line capacity
work, approval of PCOM should be taken.  
ü Administrative
approval of GM/DRM as stated below - should be obtained before incurring
expenditure on out of turn basis.
| 
Plan Heads | 
Sanctioning Powers (as per MSOP) | 
Remarks | |
| 
GM | 
DRM | ||
| 
PH 5300- Passengers &
  Other user amenities | 
2.5 Crores per case | 
2.5 Crores per case | 
Annual ceiling of Rs.25 Crores (other than
  Lumpsum grant) for non-safety items.  
This restriction is not
  applicable in case of Safety works. | 
| 
PH 5200 - Staff amenities | 
1 Crore | 
Nil | |
| 
Other Plan Heads | 
2.5 Crores per case | 
Nil | |
| 
M & P Items | 
10 lakhs per case | 
Nil | 
Annual
  ceiling is Rs. 50 lakhs.  However, all
  such proposals together with M&P items sanctioned at CME level under LAW should
  be within the Lump sum grant given by the Board. | 
ü
 The above table useful for SOP related questions in the
examination. 
                                                          *****
 