| EMD  Earnest Money Deposit | SD Security Deposit | |
| Calculated
  on  | Tender
  Value | Contract
  value  | 
| Rounded
  off to nearest higher | Rs.
  10 | Rs.
  10 | 
| Up
  to Rs. 25 Lakhs | Nil | Nil | 
| 
 Rs.
  25 Lakhs to Rs. 50 Crore | 2% | 5% | 
| Maximum
  is Rs.20 Lakhs | Maximum is Rs. 50 Lahs | |
| Above
  Rs. 50 Crore | Fixed
  Rs. 50 Lakhs | Fixed Rs. 1 Crore (Global Tenders - No ceiling) | 
| Valid
  for  | Final
  bid validity period plus
  45 days  | Date
  of completion of all contractual obligations plus 60 days | 
| If
  not submitted | Offers
  shall be summarily rejected | The
  EMD shall be forfeited and case be dealt with as that of withdrawal of offer
  by the Tenderer as per extant instructions | 
| EMD  Earnest Money Deposit | SD Security Deposit | |
| Forfeit  | If
  withdraws the Offer within validity  or  If
  not submit the balance SD within 21 days in case of awarding the Stores
  contract | In
  case of failure by the Supplier to meet deliveries for any lot, Railway may
  cancel the Contract for default part by forfeiting SD commensurate to that
  lot | 
| Exempted
  cases | 1.Up to Rs. 25 Lakhs  2.
  Govt Depts 3.
  Other Railways 4.
  Indian Ordnance factories 5.
  Railway PSUs 6.
  MSEs | 1.Up to Rs. 25
  Lakhs  2.
  Govt Depts 3.
  Other Railways 4.
  Indian Ordnance factories 5.
  Railway PSUs | 
| Exempted
  for Single Tender / PAC items | Hqrs:  1.
  Personal Approval of TAA, not below the level of PCMM. 2.
  Finance concurrence not required 3.
  Decided on case to case basis  4.
  Suitably incorporated in the Tender conditions Field
  Units:  1.
  Personal approval of TAA, but not below the SAG level  2.
  Finance concurrence is required 3.
  Decided on case to case basis 4.
  Suitably incorporated in the Tender conditions | Hqrs:  1. Personal Approval of
  TAA, not below the level of PCMM. 2. Finance concurrence not required 3.
  Decided on case to case basis  4.
  Suitably incorporated in the Tender conditions Field
  Units:  1.
  Personal approval of TAA, but not below the SAG level  2. Finance concurrence is required 3.
  Decided on case to case basis 4.
  Suitably incorporated in the Tender conditions | 
| Debarment
  - exemption in case of False declaration  | 6
  Months | 6
  Months | 
Note: 
- In exceptional
     cases, Railways reserves the right to increase the upper ceiling of
     Security Deposit, up to 10% of the contract value.
- SD clause is
     applicable - Risk purchase clause shall not be applicable 
- SD clause is
     not applicable - Risk purchase clause shall be applicable 
LD –
Liquidated damages for delayed supply
- 0.5 % of the price of stores per week or part of the
     week of delay
- Upper limit – 10% of the value of contract
     (irrespective of delays)