PG & APG in Works - Simple calculation
95 is the safety line; below it APG joins
Example: Advertised Tender value = Rs. 100
Authority: New Para 16 (4) (h) of Part II of IR Standard GCC - General Conditions of Contract for Works April 2022 Edition vide ACS 11 vide Railway Board Letter dated 13.03.2026
PG stands for Performance Guarantee & APG stands for Additional Performance Guarantee
PG & APG are calculated on the Original Contract Value (Accepted Bid Value), not on Advertised Tender Value.
95 or above → Only PG (5%)
Below 95 → PG (5%) + APG (5%)