Differences between SD and PG - Works Contracts
DIFFERENCES BETWEEN ( In Works contracts)
Features | Security Deposit (SD) | Performance Guarantee (PG) |
Object | In token for the due fulfilment of the contract | In token for the purpose of successful performance by the Contractor to execute the work. Introduced in lieu of risk action procedure (contracts rescinded due to failure of contractors) |
Due Date | EMD/Bid Security of successful tenderer will be retained as part S.D., balance will be recovered at the rate of 6 % of the bill amount till the full Security Deposit is recovered, | Obtained from successful bidder after issuance of LOA, but within 60 days of issue of LOA. a) Within 21 days from LOA – No interest b) 22 to 60 days from LOA – penal Interest 12 % per annum |
Balance | Balance Security Deposit will be recovered only from the running bills of the contract and no other mode of collecting SD shall be permitted | Submit the Performance Guarantee in any of the forms i.e., Cash, Irrevocable Bank Guarantee, Govt securities, DDs of nationalized banks, Post office SB deposit, NSCs etc. |
If fails | There is no question of failing to submit the balance SD, because the same is recovered from running bills at the rate of 6 % of bill amount till the full SD is recovered. | In case the contractor fails to submit the requisite PG even after 60 days from the date of issue of LOA, the contract shall be terminated duly forfeiting EMD and other dues, if any payable against that contract. The failed contractor shall be debarred from participating in re-tender for that work. |
Releases | Can be released subject to A. Physical completion of the work and Maintenance period if any. B. After passing Final Bill C. Obtaining the No Claim certificate from the Contractor D. Obtaining the No Dues certificate against Contractor from the Executive | Can be released immediately after physical completion of the work. |
Tuesday, February 25, 2025
Book Examination Clause
BOOK EXAMINATION CLAUSE
( IRS conditions of Contract 3300)
Meaning: The government/Purchaser to call for and verify and examine the books of the contractor/Supplier is called Book Examination Clause.
Books include Account books, vouchers, receipts, memorandum, paper or writing or any copy of or extract from any such document.
Object: Verifying or ascertaining the cost of execution of the contract.
When : before or after the prices have been finally fixed.
Contractor's duty: Afford facilities to the Government Officer concerned to visit the Contractors works for the purpose of examining the processes of manufacture and estimating or ascertaining the cost of production of the articles. If any portion of the work be entrusted by a sub-contractor or any of its subsidiary, the authorized Government Officer shall have power to examine all the relevant books of such sub- books of such sub-contractor or any subsidiary shall be open to his inspection as mentioned in clause.
Period: The Contractor or its agency is bound to allow examination of its books within a period of 60 days from the date the notice is received by the Contractor, or its agencies.
If Contractor fail to produce the Books: The purchaser can reduce the Contract price according to his best judgment. The decision of the Purchaser in regard contract price is final and binding on the Contractor and his agencies.
Result : If on such examination, it is established that the contracted price is in excess of the actual cost plus reasonable margin of profit, the Purchaser shall have the right to reduce the price and determine the amount to a reasonable level.
****