PERT & CPM ( Management Accounting )
PERT & CPM
PERT Stands for Program Evaluation Review Technique
Meaning: Concise visualization of all the individual tasks ( or operations) to complete a given Project.
Individual tasks divided into i) Events ii) Activities
All are placed in Sequential Order
Various time estimates are prepared for each activity.
The Sequence in which the activities are scheduled to be performed to create “PATHS” from the beginning to end of the Project.
The time required by the “PATHS” is determined by totaling the time for each activity along the path.
Total 3 Estimation Techniques
Most Likely (TM) - Probable duration
Optimistic (TO) – Shortest duration
Pessimistic (TP) – Longest duration
PERT formulae = TO + (4 x TM) + TP / 6
Example: TM – 15 days, TO – 10 days & TP – 25 days
PERT = {10 + ( 4 x 15) + 25} = 10 + 60 + 25 = 95 / 6 = 16 days
Critical Path Method (CPM) : Longest time path through the network will control the schedule for the entire project.
PERT & CPM – Both used to scheduling the Organization and coordinating the Project.
Events | Predecessor |
1 | - |
2 | 1 |
3 | 1 |
4 | 1 |
5 | 2, 3 |
6 | 4, 5 |
Differences between
PERT | CPM |
1.Unpredictable | 1. Predictable |
2. Non Repetitive | 2. Repetitive |
3. Suitable for R & D | 3. Suitable for Batch Costing (Rolling stock production) |
4. Time only taken into account. But Cost will not be considered. | 4, Both Time & Cost will be considered |
5. Activities represented as Lines & the Nodes Representing the Branching Structure | 5. Activities are represented as Nodes |
6. Total 3 Estimates. A. Optimistic B. Pessimistic C. Most likely | 6. Only one estimate i.e., Longest path |
7. Only one type of Activity Relationship i.e., Finish to Start | 7. Total 4 types of Activity Relationships. A. Finish to Start B. Start to Start C. Finish to Finish D. Start to Finish |
****
Monday, January 6, 2025
Friday, January 3, 2025
Exclusive Zoom Session for AFA Aspirants
Exclusive Open Session for AFA Aspirants
Date: 5th January 2025
Time: 10:00 AM
Topic: Analysis of Previous Question Papers
Eligibility: AFA Aspirants only
To register, send a WhatsApp message with "Sunday" to 8247012698.
Please note that the Zoom link will be shared with advance registrants only by 9:30 AM on 5th January 2025.
No charges apply.
All the best 👍